on 2018 Jun 22 9:19 AM
Good day
I have an issue that I do not know how to resolve. We sometimes receive 1 batch of a product in multiple shipments each with a separate inspection lot. The process is usually as follows:
1. MIGO
2. Change the User Decision (UD) under QA33 to "accepted for transfer of goods only"
3. ASN is created and stock can be received and GRNed
4. After testing release the inspection lot for sale under ZQ053
The problem comes in with the 2nd shipment, I cannot change the UD of the 2nd inspection lot if the first inspection lot is still under ZQ053. But it can take weeks to get the test results required in order to release the first inspection lot.
Any suggestions /ideas on how to resolve this?