PS TEXT updating wrongly

Former Member
0 Kudos

Hello All ,

Need your quick suggstions / help here .

I am trying to update PS text for one WBS element under project ABC, but after saving it,the text is getting updated for some other WBS element in XYZ project.

Please let me know what should i do.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I believe you are using SAVE_TEXT FM to update the Texts. You have to pass the Internal Representation of the WBS Element concatenated with "E" and pass the value to field TDNAME of THEAD. POSNR is unique to each WBS it cannot go and update some other WBS Element under a different project.

Thanks and Regards, Vinay Mutt