on 2023 Feb 27 5:23 PM
1. We would like to understand is EPPM can be used for Scheduling activates as in Primavera / MSP, if yes is there any limitations of total Activity nos. Combination of PS & EPPM will also works.
2. Is it possible to link QM module with EPPM and generate RFIs?
Request clarification before answering.
Both PS and PPM Projects can calculate a project schedule with critical path, Early/Late Dates, Total Float, Free float, Constraints, Relationships with off sets, etc.
Please explain more how the QM module relates to RFIs? By RFI's are you referring to purchasing RFIs? Projects can generate Purchase Requisitions directly but not RFIs.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for clarifying the PS & PPM, one more thing we would like to get insight from your side that is there any limitations of 9999 activities in PS/ PPM for any particular project.
Regarding QM we would like to explain below.
- We are from Construction Industry, we want to capture the Actual Start and Finish dates in ref. with RFIs (Request fro Inspection), which is possible in QM module, but linking/ integration of PS/PPM and QM is possible or not; QM only can be integrated with MM only.