Hi Colleagues,
I have made the customizing for Analytics and linked a PS project to CPM Commercial Project. Afterwards I have created Plan and Actual costs for the project. Despite this I still cannot see the project costs in the Project Cost Status (Hierarchical) view in the CPM Workspace Overview area.
Can anyone advise what setting is missing?
Thanks and Regards
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
Hi Mr. Melching,
I have created the plan costs in ERP PS using either with material planning in network activities or CJR2. The actual costs are also not displayed.
Do you have any suggestion?
Thanks
James Mendes