cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

Project Cost Status (Hierarchical) Report in CPM WS Overview in S/4HANA 1809

0 Likes
1,192

Hi Colleagues,

I have made the customizing for Analytics and linked a PS project to CPM Commercial Project. Afterwards I have created Plan and Actual costs for the project. Despite this I still cannot see the project costs in the Project Cost Status (Hierarchical) view in the CPM Workspace Overview area.

Can anyone advise what setting is missing?

Thanks and Regards

View Entire Topic
0 Likes

Hi Mr. Melching,

I have created the plan costs in ERP PS using either with material planning in network activities or CJR2. The actual costs are also not displayed.

Do you have any suggestion?

Thanks

James Mendes