Project Cost Status (Hierarchical) Report in CPM WS Overview in S/4HANA 1809

0 Likes
1,191

Hi Colleagues,

I have made the customizing for Analytics and linked a PS project to CPM Commercial Project. Afterwards I have created Plan and Actual costs for the project. Despite this I still cannot see the project costs in the Project Cost Status (Hierarchical) view in the CPM Workspace Overview area.

Can anyone advise what setting is missing?

Thanks and Regards

View Entire Topic
Former Member
0 Likes

Where did you create the Plan Costs for the project in CPM PFP or in ERP PS? If you created them in ERP, how were they created?

Are you seeing the actual costs?