Hi Experts,

I have observed that the standard SAP allows "Total demand of a role in General Tab" and "Total assign efforts to a resource" more than the working days/hours of a Task. Though it is correct because that role is created for a whole project (NOT only for 1 task) which can have multiple tasks and their working days.

Looks like, the system assumes and allows overtime hours and weekend also to assign efforts to a resource..

My client wants to avoid those both behaviour as there is no such concept of working more than 8 hrs.

How can we restrict that?

Is there any BADI for that?

Best regards,

Sandeep

Accepted Solutions (0)

Answers (1)

Answers (1)

judith_gabriel
Contributor
0 Kudos

Dear Sandeep,

To check the input of a field you can use BAdI dpr_attributes, method

VERIFY_ATTRIBUTES.


Best regards,
Judith

former_member301510
Contributor
0 Kudos
Thanks Judith.

I will check further.