Hi,
We are on PPM5.0.
Understand that cProjects replication to PS is under the profile CPR001.
In our implementation, we have more than one PS profile which would need project replication from cProjects.
How can we achieve this?
Request clarification before answering.
Hi Deepak,
In your accounting system, please implement BADI: IAOM_BUSINESS_SCENAR
Then you can use method CHANGE_PROJECT_PROFILE in order to select the right PS profile.
BR
Matthias