on 2016 Nov 17 3:59 PM
Hi ,
When we export PPM Project to MS Project then in MS Project file Instead of Latest Start /Finish Date , we are getting Earliest Start / Finish dates
Please find screen shots in attachment for "Base System Object: PDMP Sub Object: MT" , PPM Project & MSP File.
It is continuation of thread https://archive.sap.com/discussions/thread/3961724
Regards,
Manzoor Khan
Request clarification before answering.