PPM - Staffing Overview - add Project tasks

Former Member
0 Likes
880

Dear all,

I am using the staffing overview to staff roles. The problem is that the Resource Manager cannot see the Project tasks in this screen under the roles, so he can't assign the appropriate rescources.

Is there a way to add the Project task under the Roles?

Thank you in advance for your help

Regards

John

Accepted Solutions (1)

Accepted Solutions (1)

judith_gabriel
Product and Topic Expert
Product and Topic Expert
0 Likes

Dear John,

you can find information and debugging tips in Wiki page:

https://wiki.scn.sap.com/wiki/pages/viewpage.action?pageId=337709178

best regards,

Judith

Former Member
0 Likes

Dear Judith,

thank you very much for your answer.

We have debugged the staffing overview and we cannot find anywhere calling the project tasks.

Is there any customizing that should be made in order to view the tasks.

Thank you very much for your help

best regards

John

judith_gabriel
Product and Topic Expert
Product and Topic Expert
0 Likes

Dear John,

in the Staffing Overview of the Resource Management you can see the following elements:

- Project

   - Role

      - Business partner.

Tasks are not available here.

In the Resource Overview of the Resource Management you can see:

- Business partner

    - Project

         - Role

Information can you also find in the online documentation:

Resource Overview - SAP Portfolio and Project Management - SAP Library

Staffing Overview - SAP Portfolio and Project Management - SAP Library

Best regards,

Judith

Former Member
0 Likes

Thank you very much for your prompt reply.

Best regards

John

Answers (1)

Answers (1)

0 Likes

Hello,

Did you find a solution to add task to the staffing overview.

Best regards,