PPM - Responible Resurce and Sold-to-party field synchronization from PPM to PS Project

former_member301510
Contributor
0 Kudos
278

Dear Experts,

I need to update and synchronize the following fields' values from PPM to PS Project definition.

PPM Project PS Project

Responsible resource Person Responsible

Finance controller (as a resource assigned to a Role and Role Function) Applicant

PMO (as a resource assigned to a Role and Role Function) PMO (as a Partner in Partner tab of Project definition)

Sold-to-party Sold-to-party (as a Partner in Partner tab of Proj. Def.)

Can anyone suggest me a relevant exact BADI to achieve that synchronization?

Best regards,

Accepted Solutions (0)

Answers (2)

Answers (2)

judith_gabriel
Product and Topic Expert
Product and Topic Expert
0 Kudos

Dear Sandeep,
You can follow up the steps as described in KBA note 2687886 - to receive the custom fields in the customizing of DFM attribute synchronization.


Best regards,
Judith

judith_gabriel
Product and Topic Expert
Product and Topic Expert
0 Kudos

Dear Sandeep,

You can try to achieve your expected systembehaviour by usage of DFM attribute synchronization. Otherwise, you can use BAdI INM_OF_SYNC to transfer the data.

Best regards,

Judith

former_member301510
Contributor
0 Kudos

Thanks a lot Judith for your response.

I was waiting your expertise in one another thread as well.

Would you please respond on this also?

https://answers.sap.com/questions/12890554/ppm-automatic-account-assignment-to-ps-elements-us.html

Regards,

former_member301510
Contributor
0 Kudos

Hi Judith,

I am not sure if you read that 'Sold-to-party' and 'PMO' are configured and maintained in PS project by using Partner determination procedure. So, those fields does appear in PS project definition as Partner type under 'Partner tab'.

Attached screen shot.

In that case also, will that BADI INM_OF_SYNC work?

Regards,