PPM or EPPM for investment controlling instead of SAP IM

bjoern_hansen1
Participant
0 Kudos
2,109

Hi all,

I have heard, that SAP IM (investment management) is not the target architecture by SAP, but EPPM (or PPM?).

a) is this true?

b) where can I find an official statement like this?

c) customer has already PPM, but needs similar functionality like SAP IM, problem: e.g. an IT project has 80% OPEX and 20% CAPEX. Capex shall be planned/budget/reported in an own structure (like IM23). I was told, it is not possible to assign a project or WBS element to 2 different hierarchies (portfolios?) in PPM. this should be a common situation at customers...

Any help highly appreciated

best regards

Bjoern

View Entire Topic
bjoern_hansen1
Participant
0 Kudos

Hi Ken,

thanks for your answer. On PS side everything is clear to me. General recommentation is to have 2 different WBS for CAPEX and OPEX (even if this needs reposting of costs).

this leads to the question: I have a clear assignment of WBS elements (object class) to CAPEX or OPEX. CAPEX is centrally managed (investment controlling). Availability control is not needed in ERP/S4, but reporting on planned and "used" investments = actuals on CAPEX WBS elements.One site currently uses SAP IM (IM23) with IM32 and IM52...

Beside availablity control, which is not required, the question is, if eppm (is that the new functionality in S4?) can provide this kind of functionality, like top down allocation of budget (=plan figures in S4/ERP)?

Is this something the classification could provide as kind of "alternative hierarchy"?

many thanks!

br Bjoern