PPM - DFM Status Synchronization from PS to PPM

former_member301510
Contributor
0 Kudos

Hi Experts,

I am trying to synchronize PS project statuses to PPM Portfolio item statuses.

REL ---- REL, TECO---TECO, CLSD---CLSD, Undo TECO----REL and Undo CLSD----TECO.

I could able to achieve REL status synchronization from PS to PPM.

Also, I am able to synchronize TECO.

Can we synchronized both TECO and CLSD because there is only one relevant DFM Transaction i.e. 'Complete'?

I believe, we can synchronize both TECO and CLSD to only one 'Completed' status in PPM. Right?

I have tried all the required configuration but no success specially for "undo TECO" and "undo CLSD" statuses.

Kindly suggest. Attached config. screen shots.

Thanks in advance.synch-config.jpg

Regards,

former_member613562
Participant

Hi Sandeep,

I achieved the same by using the following Business Transaction

1) TECO - use BTAB

2) Undo TECO - use BUAA

3) CLSD - use BABS

4) for Undo CLSD - I don't remember the exact business transaction, take the help of abap resource to find out the exact business transaction and maintain the settings accordingly

Thanks and Regards

Accepted Solutions (1)

Accepted Solutions (1)

former_member301510
Contributor
0 Kudos

It has been resolved.

I selected status "CLSD" as end status so the system was not allowing undo CLSD.

Answers (1)

Answers (1)

former_member301510
Contributor
0 Kudos

Basically, I am looking for corresponding DFM transaction to be mapped for BTAB, BABS, BUTA and BUAB in Config. "Map Project/Initiative business transaction to DFM Business Transaction".