Hi Experts,
We used a BADI “GCC_PS_PROJECT_DATA “method “MOD_WBS_ELEMENT_DATA_C” to create automatic project/WBS elements in PS corresponding to PPM project elements using Accounting integration functionality.
Also, we maintained controlling level as ‘1’ in Controlling scenario customization but we could able to create WBS elements till Level 4 in PS.
Also, the resources' costs from PPM is getting transferred on L1 WBS level in PS using ECP.
In standard, L1 WBS element itself gets account assigned automatically to all the project elements (Project def. Phase, Tasks) in PPM. By that, all the resource planning costs (using Ad hoc cost estimate/Easy Cost planning) transfers and appears against L1 WBS element itself in PS.
Our requirement is that we want to transfer individual resources' costs (in task) to respective WBS element (NOT L1) via ECP.
Is that really possible???
e.g. (Table stable-should-appear.jpgcreen shot attached)
It should appear:
PPM PS Amount
Phase L1 WBS 7500 USD
Summary Task L2 WBS 7500 USD
Sub-task 1 L3 WBS1 2500 USD
Sub-task 2 L3 WBS2 5000 USD
Please refer attached screens for existing behavior.
account-assignment-and-ecp.jpg
Regards,
Request clarification before answering.
Sorry not in standard. In standard PPM /PS Cost integration the ECP cost is aggregated at L1 level only..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.