on 2018 Aug 13 9:58 PM
Hello Everyone,
Does anyone know why the priority value of the task is not getting displayed on the tasks dashboard on "My Tasks" tab?
The priority of any project is displayed correctly on the projects dashboard.
Mohan
Request clarification before answering.
Hi Mohan,
it seems that the evaluation customizing is incomplete. Ensure that object 'Task' is correctly maintained in following customizing:
Transaction SPRO:
> SAP Portfolio and Project Management
> Project Management
> Evaluations
> Define Attributes and Object Types for Evaluations
- go to "Attributes"
- select "PRIORITY"
- go to "Objects for Attributes"
Make sure that object category TASK is assigned. Afterwards, trigger the evaluation.
See also SAP Knowledge Base Article 2462344.
Regards,
Silvia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Any input is appreciated.
Mohan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.