on 2018 Jul 11 4:46 AM
Hello Everyone,
I am able to complete the phase without completing/Cancelling the tasks. I could set a mandatory check for the tasks on the additional data tab but it is only relevant for the status complete not cancel.
I am not able to complete the phase if the mandatory task has a status cancel.
How do I allow mandatory tasks to have either complete or cancel status and still able to complete the phase?.
Mohan
Request clarification before answering.
Hello Mohan,
I see two possibilities:
Best regards
Francesco
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Francesco,
1. "Relev. for App" checkbox is not available because I had to disable the "Approve Phase" at the phase level due to no Adobe Document Server. The only option left is to check the mandatory checkbox at the task level then every task should have a "Complete" status to set the phase status to "Complete".
I assume I can't have the "Approval" tab without an adobe document server?.
2. I am not sure if I want to take this route.
Regards,
Mohan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Mohan,
I agree that the option 1 is not viable if you are not working with approvals (even if your aim were to stop you from cancelling these tasks at all, which is what this approach would do).
This leaves you with option 2. As the checks for mandatory tasks with status "completed" is hardcoded in the method which I mentioned in my earlier reply, there is unfortunately really no other way to change this standard system behaviour than to change the coding via customer enhancement.
Regards,
Francesco
User | Count |
---|---|
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.