on 2022 Sep 05 1:18 PM
Hi,
For one of our portfolios in PPM, we link PPM items to PS projects (from a different logical system) to synchronize master data.
However, in this case PPM and PS are not on the same system.
However, we would also like to synchronize the following master data fields from PS to PPM:
- Planned Start
- Planned Finish
- Actual Start
- Actual Finish
So, whenever the value in the above fields in the PS project changes, it needs to be directly and automatically synchronized to the corresponding PPM item master data fields:
- Planned Start
- Planned Finish
- Actual Start
- Actual Finish
And also we would like to synchronize PS system status CLSD to an item header status.
Is it possible with standard DFM in PPM to synchronize master data and system status from the PS project to the PPM item when PS and PPM are not in the same system?
Hi,
In the online documentation under "Synchronization" you can find information about DFM attribute and status synchronization.
https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/db719753e69f4e8eb9902aaea0fd8471/4ac386668c352470e10...
It´s possible to synchronize attributes and status from PS-Project to Item - also when different systems are included. An example for attribute DFM
synchronization can you find in the Wiki under https://wiki.scn.sap.com/wiki/pages/viewpage.action?pageId=449905597
Best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
5 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.