on 2010 Dec 22 1:44 PM
Dear all
In cProjects version 4.0, we have integration with existing ECC 6.0. We create Internal Order manually and assign it to cProjects.
One cProject having one Internal Order.
Resource Planning part is managed in cProjects while Actual Time keeping(CATS with reference to Internal Order), budgeting of Internal Order, Material and Service Procurement which is done against Internal Order is managed in ECC. ECC and PLM are separate systems.
We have RFCs established to transfer actual hrs, budget and actual cost data from ECC to PLM.
Which is the ABAP table in PLM where we get linking of cProject with Internal Order and also actual hrs, budget and actual cost data in PLM system?
Thanks & Regards
Ashish
Request clarification before answering.
actual hrs, budget and actual cost data in PLM system?
Its not there, actual hours can be found in DPR_Task but it needs to be transferred by running a report.
The planned cost etc is also calculated at runtime and passed on to Costing object in ECC (Int order/PS)
Actual hours will be in CATSDB in ECC
needless to say actual cost will also be there in ECC and not in PLM, PLM only displays at runtime based on RFC.
If you want to try, Break the RFC and try to check the Evaluation..
Niranjan