Plant "phased" roll out of SAP S4/HANA for Product Compliance

Paulo_Pinto
Participant
0 Kudos
383

Dear SAP S4/HANA for Product Compliance

My customer is a multi-company conglomerate and is now considering a "phased" roll out (and go live) of SAP S4/HANA for Product Compliance (PC and PMA) by plant: first "1100", then "1200" and so on. 

EDIT: All of this different companies are all on the same system, with their own plant code. It's S/4HANA on-prem, 2023 release, and it's PC "new". 

How can I make this work? Is it possible with SAP S4/HANA for Product Compliance?

It might be a silly doubt at this point, but humbly request your assistance.

Thank you

Paulo 

View Entire Topic
christoph_bergemann
Active Contributor

Hello

sorry to say.. this is not possible.... The activation of PC (Product Compliance) (and therefore move from EHS Classic to PC) can only be done by "process" (and not by plant, company code or whatever similar criteria)

C.B.

PS: Best knowlegde on my side: something like you would like to get is not on the roadmap of SAP and from my point of view will not come to the Roadmap of PC solution

PPS: honestly: this question you could ask SAP:

What i could imagine which might work (but please ask SAP): you have one S/4 HANA system: You have two clients. In Client X you use EHS Classic and in Client Y PC; but if this help... no idea

Paulo_Pinto
Participant
0 Kudos
Thank You Christoph! That's what I was afraid...