Hi all.

I have been using SAP to plan our maintenance for 3 years, and the way that I do it is:

- IW38

- Extract the list of w.o

- Sort the Maintenance schedule with this list

THe problem is, it does not come with the work hours per work order. Recently, we realized that we must have these hours in order to have good planning, but I can't find the correct Tcode that would give me the work orders list and the sum of hours per document.

My question is, how does an SAP professional recommend the maintenance planning of a plant to be done? What are the correct Tcodes and process to be followed?