cancel
Showing results for 
Search instead for 
Did you mean: 

place done SFC qty back in production in order based scenario

Former Member
0 Kudos
174

Hi

I am looking for a way to return SFC done quantity to production.

We are working with relaxed Routing (order based Scenario), where one SFC can be spread out over several operations, e.g. OP1 50 pc. - OP2 30 pc. - OP3 20 pc. (only active quantity for simplification reasons)

When completing partial qty on last Operation OP3, e.g. 10 pieces that quantity is DONE. Up to my research there is no way to bring that quantity back to production, e.g. because completed the quantity by mistake

I tried the following already:

  • NC logging via POD: not possible b/c done quantity cannot be accessed via POD
  • NC standalone logging: not possible b/c selection of SFC, Operation, and Status done not possible
  • SFC quantity adjustment: not possible unless full SFC quantity is in Queue at one Operation
  • SFC Step Status: does not allow to select done SFC quantity

Does anyone have any suggestions what else to try?

Thanks

Ulrike

Accepted Solutions (0)

Answers (1)

Answers (1)

williamson
Advisor
Advisor
0 Kudos

Hi,

If you want to use step status to change a 'Done' SFC then you must first change the rule 'ALLOW_SFC_MARKED_DONE' for activity SU500, to YES using Activity Maintenance.

Thanks

Steve