on 2009 May 07 2:42 PM
Hi
When we release the project the phase below the project also change the status from Create ---> Released.
but in some case it don,t change the status it will remain in Create status . Any one have any idea why system shows such behavior or is there any table entry missing . SAP note to improve such things.
E.g.
Project : SUN AX1010 D --> Release
Phase : CANCEL_PENDING --> Create ( it should be release as we release the project)
Thanks
Sunil
Request clarification before answering.
HI Sunil,
Is this issue resolved.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
CLOSED
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunil,
Please go through Phase setting
Release Successor Phase Only After Approval
If you set this indicator, you can only release a subsequent phase if the current phase has the status Approved.
If you do not set this indicator, the system only checks whether the current phase has already been released when releasing the subsequent phase.Are you using stage gate methodology?
Please check Phase setting for both project
Regards
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunil,
has a Phase Type been maintained? Unless this has been done the phase can't be released, but a respective message should be shown in the log. Is the log free of any such messages?
Best regards,
Thomas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hello,
cProjects works on stage gate methodology. One u release project first phase of projects gets automatially released. The successor Phase of this phase gets relased only after all te tasks and checklist Items are released / completed.
Regards,
Pramod
plz rewrd pts if its useful / solve ur query.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunil,
As Simmi has rightly said please check the status for the Task and the Checklist items below that Phase.
Go to http://help.sap.com/saphelp_ppm450sp04/helpdata/en/43/054880bbe822f5e10000000a1553f7/frameset.htm for more details.
Hope this will solve your query.
Regards,
Nishit Jani
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do you have tasks/check list items below the phase that are not released??
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.