Phase Overlap in SAP PPM Project

Former Member
0 Likes
422

Hello Experts,

We have a scenario in PPM Project in which we need phase overlap in scheduling. Currently system takes 2 phases in Pred-Succ mode. Can BADI DPR_SCHEDULING solve this issue?

Experts please help!!!

Nachiket

Accepted Solutions (0)

Answers (1)

Answers (1)

judith_gabriel
Product and Topic Expert
Product and Topic Expert
0 Likes

Dear Nachiket,

you can use BAdI DPR_SCHEDULING with method STRICT_BOTTOM_UP to allow overlapping of phases.

Information can you find under "solution" in SAP Note 1150146.

Best regards,
Judith