on 2022 Feb 21 5:13 PM
Hi Experts
our Requirement is to get an Alert Notification to the phase Approver if the phase is not approved for more than one day. is it possible through Severities in ppm. please Suggest on the approch.
Regards
Gopi.
Request clarification before answering.
Hi Yaswanth,
I think that the solution to what you are raising has two steps:
1º.- Define the logic of the alerts by severity of evaluation in Project Management->Evaluations....
2º.- Define the workflows and recipients in Portfolio Management->Global Customizing->Global settings->Workflow Settings->....
I hope it helps you.
Example:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can use a workflow to do this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.