on 2019 Apr 05 11:56 AM
In our system, production order are released from ECC with routing details. As, SAP ME supports parallel operations/simultaneous sequence if we create operation routing using routing maintainance. We can have normal/standard sequence and parallel/simultaneous sequence in same routing for operation in SAP ME.
But, when we release order from ECC with parallel sequence and standard sequence operations in routing, standard sequences worked as expected but, parallel operations are also being treated as normal sequence. We have modified LOIPRO XSLT to accomodate parallel sequence but, not working.
Has anyone done integration of SAP ECC with SAP ME for parallel operations?
Request clarification before answering.
Hi Apoorv,
Parallel sequencing of operation is still not supported in SAP ME.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Parallel sequences are not supported yet, though are in plans for future releases. Usually, a customization to XSLT in SAPMEINT is needed to create simultaneous groups in routing on side of SAP ME based on Control Key grouping for example.
Regards,
Sergiy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.