on 2020 Nov 09 1:13 PM
Hi,
Where can i see (if available) the Operation start and complete time in S/4 for an operation executed in SAP ME?
I believe this information should be part of standard yield confirmation idoc.
Please suggest?
Regards
Imran
Hello Imran,
Go to "Monitor production / Planned orders" app or T-code: COOIS , Select the List as "Confirmations" and then execute the Transaction.
Once you see the output, goto -> change layout - > add required fields ex. Actual Start time and Actual finish time.
Regards,
Kumar Semmalai