Not able to change workcentre in SAP MII (OEE)

radulani
Explorer
0 Kudos
1,222

Hello Experts,

We have implemented SAP OEE along with SAP MII.

We have the following scenario-

Once the order is released and it is in MII, there is a chance that the supervisor wants to change the work center of a routing operation due to various reasons. If we change the work center in ECC, it is successful in ECC, it also triggers a new IDOC to MII, however on reaching MII, it is giving the following error-
"Production Order cannot be saved:" in the Queue Monitor-

And in the log viewer, we get the following error message-

Can someone please clarify what exactly is the issue here? Are we missing out on some configuration or as part of the standard MII OEE solution offering, work center change is not allowed in between the production order process?

Please note- this same error is encountered for the orders which are in RELEASE status and have not been started.

Please advise if there is any workaround for this issue. Thanks.

Regards

RD

Accepted Solutions (0)

Answers (2)

Answers (2)

Mahalakshmi1
Participant
0 Kudos

HI,

OEE doesnt support the workcenter change as a standard feature. even customizations to achieve this feature would need to touch at the table level though that is not the recommended option.

Thanks

Mahalakshmi Syamsunder

ankit12
Active Participant
0 Kudos

Hi Experts,

did you find any solution of the above issue. Same we are facing now.

As per my understanding,

  • if Process order is started in OEE (Status is Active)and then they want to change the resource/Operation then it should fail.
  • But if Process order is in New status (Status is NEW)and then they want to change the resource/Operation then it should allow us to change it

Could you please provide some insight and how to overcome of this issue if process order is in new status in OEE.

Regards,
Ankit Gupta

ankit12
Active Participant
0 Kudos

@michael.appleby, could you please help us on this?

mertturfanda
Explorer
0 Kudos

Yes, it should be exactly like you described. The release function must be at operation level, so if an operation is not started yet, the work center could be changed. Right now, even the operation is not started yet, system is checking the MPM_AFKOL table which is at order header level.

However i think no one knows or can help at this point unfortunately.