on 2018 Mar 04 12:16 PM
Hi,
We're on PPM 6.1 and would like to process decision point in non sequential manner. We're aware about the non sequential phase processing, which can be enable using by setting value for area 0012 setting name 0002 in Override Default Global Setting.
e.g. Portfolio item A has decision point A1,B1,C1. Sometimes instead of closing A1 we may start decision point B1. Or chances are also there where we may not start decision point B1 at all instead go to C1 and in B1 give some details about skipping it. Meanwhile Decision point A1,B1 and C1 remains open and allow changing there statuses/details.
So are there any BADI/Switch setting are there for the same?
Regards,
Alex
Hi,
Did you manage to find the solution for the issue, as i am facing the same issue with my client for parallelly processing of decision point
how did you managed to resolve it
Thanks and Regards
Simon Walter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Alex,
The current program design allows to edit the attributes (e.g. dates) for successor decision points, and if you set global switch
0007/0011 it also allows to edit predecessor decision points (i.e. decision points with completed status). The actual processing of the decision points (i.e. the order in which they decome active) however is strictly sequential. There is no switch to change this behaviour and I am not aware of any BAdI which would allow you to do so.
Regards
Francesco
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.