on 2013 Aug 26 2:33 PM
Hi All,
In Risk Type we have 3 stanard Risk type
1. Initial Risk
2. Resudual Risk
3. Inherent Risk
Now in Assessment Steps I have created Multiple Steps for each Risk Type, but the problem is when i select the 2 step in the same risk type the data is loaded in the Risk Matrix from 1st Step. But when I select the 2nd Risk type the Risk Matrix is fresh.
So can any one please let me know how to get fresh risk matrix for the same risk type.
------
The following ways i have tried but not sucessfull
1. Created New Risk type by enhancing the Domain fixed values.
2. Created a New Variant in the configuration and assigned that variant in Assessment Steps.
Thanks and Regards,
JK
Request clarification before answering.
I don't think the solution can do this with only configuration.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi jayakumar.
i am not sure what you are looking. would you be more specific? Are you using the risk assessment in the component extension or classic version?
As per your question, you are trying to Created New Risk type by enhancing the Domain fixed values. What is this Domain fixed values?
Please provide if possible some prntsc.
Edward
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Edward,
Thanks a lot for your response.
Have attached the screen shot . Please have a look at it.
Have Created Multiple Steps in Assessment Steps
è Determine Inherent Risk – People
è Determine Inherent Risk – Assets
è Determine Inherent Risk – Environment
è Determine Inherent Risk – Reputation
sd
ad
Now I select a value Say “48” in the risk matrix and then go for the next step “Determine Inherent Risk – assets” then by default the Risk Matrix is loaded with “48” value. Whereas when I select the “Determine Initial Risk – People” then a fresh matrix is loaded where the user can select the value.
In SPRO settings have added the steps as shown in below picture.
In Domain “EHHSS_RISK_ANALYSIS_TYPE” I have added the new fixed value.
Kindly help me.
Thanks
JK
Hi Edward,
Thanks a lot for your response.
Have attached the screen shot . Please have a look at it.
Have Created Multiple Steps in Assessment Steps
è Determine Inherent Risk – People
è Determine Inherent Risk – Assets
è Determine Inherent Risk – Environment
è Determine Inherent Risk – Reputation
sd
ad
Now I select a value Say “48” in the risk matrix and then go for the next step “Determine Inherent Risk – assets” then by default the Risk Matrix is loaded with “48” value. Whereas when I select the “Determine Initial Risk – People” then a fresh matrix is loaded where the user can select the value.
In SPRO settings have added the steps as shown in below picture.
In Domain “EHHSS_RISK_ANALYSIS_TYPE” I have added the new fixed value.
Kindly help me.