Hello,

Here is my requirement : If i logg several NC code towards an SFC on the same operation, each NC code have a disposition routing.

At operation complete (add-done), the operator can choose the disposition routing he want ot process :

Problem is the following : once i finish the disposition routing, i get back to the production routing & I don't go to the next disposition routing.

Question : is it possible to queue disposition routing?

Thanks in advance

Accepted Solutions (0)

Answers (1)

Answers (1)

sergiy_katerinich
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi!

Only one disposition is allowed per the Log NC session. So, if you need further disposition at the end of NC routing, you should either log a new NC Code with such disposition, or assign a Disposition Group to the NC routing in Routing Maintenance (then such Disp Group will be triggered at the end of NC routing each time).

Regards,

Sergiy