Dear All,
We are testing the MS Project Integration with cProjects 4.0. We have 1 query.
While importing the Project from MS Project to cProjects if changes are done then it creates the new project in cProject system.
Is it the standard MS Project Integration functionality ? We want the system to update the cProject only for the changes after Import is done. Can we get this ?
Thanks & Regards
Ashish Kulkarni
Request clarification before answering.
The system will create a new project only if you have cleared the Project ID field (in MS project).
Else (if you do not change the Project ID field), the system creates a simulation with the standard system provided simulation for the project.
Once you have the simulation ready (in cProjects), you are supposed to reconcile the operational project (main project in cProjects) with this simulated copy to bring the updates/changes into effect.
Hope this helps...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.