MS Project Integration with cProjects

Former Member
0 Likes
181

Dear All,

We are testing the MS Project Integration with cProjects 4.0. We have 1 query.

While importing the Project from MS Project to cProjects if changes are done then it creates the new project in cProject system.

Is it the standard MS Project Integration functionality ? We want the system to update the cProject only for the changes after Import is done. Can we get this ?

Thanks & Regards

Ashish Kulkarni

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Likes

The system will create a new project only if you have cleared the Project ID field (in MS project).

Else (if you do not change the Project ID field), the system creates a simulation with the standard system provided simulation for the project.

Once you have the simulation ready (in cProjects), you are supposed to reconcile the operational project (main project in cProjects) with this simulated copy to bring the updates/changes into effect.

Hope this helps...

Former Member
0 Likes

could you please guide me the process of both ways synchronization for cProject and MS project.

Thanks in inadvance

Former Member
0 Likes

Refer to these notes. These contain exhaustive details of the integration.

958210 for MS P client integration

983597 for MS P server integration

1126395