I am using MRS version 10 and use a scenario for automatic resource assignment. When in my order operation i have assigned 2 or more resources i expect that the automatic assignment is searching for multiple resource and makes an assignment to these multiple resources. This is however not the case only one resource is assigned. How can we get a correct assignment?

Accepted Solutions (0)

Answers (1)

Answers (1)

BWA
Explorer
0 Kudos

We did not solve the issue. Process was redesigned to stick to standard. Second operation was created for second assignment