Dear MRS experts,

We use MRS 10.0 to plan PM/CS service orders.

We would like to know if a feature like a "mass planning" exists?
Our goal is to assign several demands (let's say 5 or 6) to a resource in one step.

We do not need something very complicated. Simply being able to select several demands and assign them to a resource (in one step) is sufficient. We expect the demands to be assigned to the resource in sequence (simply one after the other).

Is there a way to achieve this?

Thank you

Regards,
Philippe

Accepted Solutions (1)

Accepted Solutions (1)

philippe_tsalos
Participant

Problem solved by myself.

For the record, I have achieved it by customizing the automatic creation of assignment in MRS customizing:

  • Sources of Demand -> PM/CS Orders -> Control Automatic Assignment Creation (ERP)
  • Sources of Demand -> PM/CS Orders -> Define Search Strategy for Automatic Assignment Creation (ERP)


I also activated the possibility to select several items in the Worklist.

Regards,
Philippe