on 2024 Jan 29 7:18 AM
@former_member121014 System Generating duplicate planned order where strategy is maintained 82 and in MRP4 Collective/Individual is maintained 1
System is again generating a planned order against that sale order which is not required
All MRP parameters are maintained properly. This error shows only for some of the Materials, What could be the possible reason for this.
Request clarification before answering.
By using this Note problem has solved.
1745312 - MRP creates redundant proposals though there are fixed future receiptswhich can cover the requirements.