MRP GENERATING DUPLICATE PLANNED ORDER FOR STRATEGY 82 IN MD04 AGAINST SALE ORDER

bhawaniswain1
Explorer
0 Kudos
355

 

@former_member121014 System Generating duplicate planned order where strategy is maintained 82 and in MRP4 Collective/Individual is maintained 1 

bhawaniswain1_0-1706511927245.png

 

System is again generating a planned order against that sale order which is not required 

bhawaniswain1_1-1706511982333.png

bhawaniswain1_2-1706512180175.png

 

All MRP parameters are maintained properly. This error shows only for some of the Materials, What could be the possible reason for this.

 

Accepted Solutions (1)

Accepted Solutions (1)

bhawaniswain1
Explorer
0 Kudos

By using this Note problem has solved.

1745312 - MRP creates redundant proposals though there are fixed future receiptswhich can cover the requirements.

 

 