on 2023 May 24 11:04 AM
Dear Experts,
System allowing me do the Production order confirmation (goods receipt) without goods issue in MIGO against the production order.
Kindly help how can we make MIGO 261 movement (good issue) mandatory before confirming the production order.
Thanks
Request clarification before answering.
Hi,
Please refer to this link MIGO Good Issue Mandatory before Production Order Confirmation same question was asked here.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
amitj123
In order to make MIGO 261 mandatory in SAP Quality Issue Management, you will need to go to the production order and select the checkbox to enable the "Require goods issue" option. This will ensure that goods will only be issued after a production order has been confirmed. Additionally, if you are using the Inspection type 5 (Post goods issue) then the goods issue is mandatory before completing the inspection.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
2 | |
1 | |
1 | |
1 | |
1 | |
1 |