Hi,

Entry length is incorrect. "C-00/000-00"

Message no. CJ610

Diagnosis

The key that you entered for the project definition or the WBS element

does not have the same length as was entered in the coding.

System Response

Processing stopped.

Procedure

Enter the key as it was defined in the coding of the project definition

or WBS element: "C-00/000-00".

Could you guys let me know where exaclty i need to default to coding mask for creating the wbs element from the cProjects.

Rgds

Sudhir

Accepted Solutions (1)

Accepted Solutions (1)

silvia_kreuzhuber
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Sudhir,

the relevant transactions (in the ERP system) for maintaining a coding mask are OPSK and OPSJ. These transactions belong to the 'PS' (project system) application component, if you have further questions with regard to the masks, I would recommend to post them in the PS forum.

Regards,

Silvia

Answers (1)

Answers (1)

Former Member
0 Kudos

it was a coding mask key issue.

Former Member
0 Kudos

Hi Reddy,

As I understand your problem that your trying to integrate Cproject with Project ( From PS module)

Scenario --> PS Structure will be Automatically Created in Cproject.

It is important to Define a project number which fits with the Customizing setting of project edition mask in PS . The project number defines in cproject is transferred exactly to PS.

For Example:

Step : Spro --> project system -->Structure -->oprative structures --> work break down structure --> @ Define project coding mask

In that check the available project Number

The following characters are available for editing:

X for alphanumeric characters

0 for numeric characters

special characters to organize the project numbers

e.g Project coding key : SUN

Coding Mask :-000-00-00

Then you define the project definition as : SUN-100-01-00

When you define project number in c project use this mask code ( check which mask code are define in your system and use that)

and same will be created in your PS with same as project definition

Please let me know if you want any help for Cproject and PS integration.

Thanks

Sunil