on 2018 Feb 20 2:18 AM
In every Month After scheduled of Maintenance order inside Operations tasks the actual work cell is not in white color to edit & its not calculate any no.s
I don't know why ?
Request clarification before answering.
Hi,
Additional to Pete responce, Actual work will be updated based on your confirmation.
If possible share the screenshot of the information you are looking for.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The Actual Work field (AFVGD-ISMNW) on the operation should never be open for data entry.
The field is summated from the confirmation data (IW41).
Check to see if you are using BADI IWO1_SCREEN_MODIFY. If so, deactivate it to see if the standard functonality returns.
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.