Maintenance Order Operation task wise the Actual work is not calculating

Former Member
0 Kudos
248

In every Month After scheduled of Maintenance order inside Operations tasks the actual work cell is not in white color to edit & its not calculate any no.s

I don't know why ?

Accepted Solutions (0)

Answers (2)

Answers (2)

MTerence
Active Contributor
0 Kudos

Hi,

Additional to Pete responce, Actual work will be updated based on your confirmation.

If possible share the screenshot of the information you are looking for.

Regards

Terence

peter_atkin
Active Contributor
0 Kudos

The Actual Work field (AFVGD-ISMNW) on the operation should never be open for data entry.

The field is summated from the confirmation data (IW41).

Check to see if you are using BADI IWO1_SCREEN_MODIFY. If so, deactivate it to see if the standard functonality returns.

PeteA