on 2018 Feb 20 2:18 AM
In every Month After scheduled of Maintenance order inside Operations tasks the actual work cell is not in white color to edit & its not calculate any no.s
I don't know why ?
Request clarification before answering.
The Actual Work field (AFVGD-ISMNW) on the operation should never be open for data entry.
The field is summated from the confirmation data (IW41).
Check to see if you are using BADI IWO1_SCREEN_MODIFY. If so, deactivate it to see if the standard functonality returns.
PeteA