Hi everyone,


I´m currently looking for a solutions where PMS ist linked with BPM Software, that the Data can flow thrue and everyone can stay in his own system (to explain it short).

Is there any solution from the SAP, for example with PS/ PPM and Change records?

Thanks in advance for your help!

Accepted Solutions (1)

Accepted Solutions (1)

sammar81
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Leo,

You can do an object linkage of PPM item to PLM change records or cproejcts Tasks to Engineering Record. . Thereby navigating between the two.. if that helps you in your integration..

Regards

Sammar

Answers (1)

Answers (1)

former_member689423
Discoverer
0 Kudos

thanks Sammar,

that was the answer I was looking for!