Hi Experts,
I have the following situation in PPM5:
We are managing a PPM which represents a project. We want to link PS project to Item using object link.
Question : Can I link 3 Projects in PS to Item using object link and will the cost of all three get summed at item level .
E.g. We have 3 projects in PS
And we have item as Mobile implementation can we link all three project to one item and get the cost for mobile implementation as sum cost of 3 Project in the financial Planning
Thanks in advance.
Ashish
Request clarification before answering.
Hi,
In addition to above information, if the main purpose is achieve financial data update at item level then I believe only option no 2 from above message is possible. Through object linking option, I doubt you can achieve financial data update at item level with standard system.
Regards,
Pramod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ashish,
You can assign the project to portfolio item via 2 options
1) Via Relationship->Object Link - Any no. of projects can be assigned through this option.
2) Via Relationship ->Related Objects - Only one project can be assigned through this option.
If you are using automatic PS project creation from portfolio item, single project via option Relationship ->Related Objects will be created automatically.
Cheers
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.