on ‎2011 Nov 10 4:17 PM
Hi,
Is there any limit in the number of activities that can be ceated inside a project in cProject module?
Regards
Request clarification before answering.
Hi Jorge,
There's no technical restriction, BUT SAP recommends not to exceed 1000 project elements per project in order to guarantee good response time.
A project element can be: phases, tasks, (mirror tasks must be counted twice) checklist items, roles, resources and so on.
Please check SAP Note: 756670.
BR
Matthias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
My main customer is facing right now huge problems of performance due to big projects with more than 2000 elements.
So it is crucial during your prototype phase to simulate one project close to the major ones that could be run by your end-users, in order to confirm the response time.
BR
Matthias