I am trying to complete a basic finish date mass change on a number of work orders using the mass change function. I would like to increase the basic finish date by 30 days, but i cannot get the formula function to work.
The work orders all have different existing finish dates, so I do not want to change them all to the same absolute date, rather increase them all relatively by +30days.
Is there a way to do this?
Thanks, Nikki