on 2006 Dec 07 8:42 AM
Dear All,
We are working on cProjects 4.0 with ECC 6.0,
Trying to do Accounting Integration.
For only one Project I am able to create Internal Order,
But I am getting following error.
Cost/revenue rate YP002 is not valid in organization 00000000
Inspite of assigning these rates to the organization 00000000
For other projects, when I click on accounting:
I get following error
"Single-Obj.Controlling on InternalOrders 0188993B3E343947A046B554FD886E03 000006000032 does not exist"
When I go to Controlling Cockpit, I see this Internal Order not being created.
Have revisited all settings, project type, etc.
How do I go about this.
Kindly help,
Navendu
Request clarification before answering.
Hi,
Refer OSS Note : 875275
Regards,
Reema.
Reward points for useful answers.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
I was able to solve the one of the problem, with the following settings,
Assign Cost Elements & Activity Types:
Choose Organization, Start & End Dates, Cost and Revenue Elements, Currency.
The start and end date of the cost/ revenue did not fall within the start and end date of the Organization.
Regards,
Navendu Shirali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.