Hi Gurus,
We are trying to pass cost and revenue related to a project from ECC to RPM with the program RPM_FIN02, but when we are executing the program we find out the IDOCS has not been created. Why this happen? am I doing something wrong?
Regards,
MC
Request clarification before answering.
1. Make sure that xRPM item has a object link for SAP PS Project ( object type 0RPMFIPROJECT). When you run the program in ECC, it makes an RFC call to xRPM system to read object links of the project specified in RPM_FIN02 program.
2. Make sure that you are specifying xRPM project id in Project ID field ( not the SAP PS Id).
3. Check your ALE settings.