cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

Integration cProjects 3.1 and SAP PS/CO

Former Member
0 Likes
218

Hi all,

I’m working with cProjects 3.1, <b>not installed in CRM Platform</b>. At this moment I have accounting integration, the system create an internal order to collect the costs.

My doubt is:

If I want to install the cProjects 3.1 in the CRM platform, I’m going to have the PS integration (costs and revenues are collected on the Project WBS), but I’m going to lose the accounting integration (internal order) or not?

It’s possible the multi-object integration (Project and Internal order)?

Thanks,

Alexandra Pires

View Entire Topic
Former Member
0 Likes

Hi,

When you switch over to the CRM platform, you do not lose the internal order functionality. However when you convert the cProject to PS project the costing gets captured at the WBS level.

Regards,

Amit