In IH&S -> Work Area Management -> Specify Operation Statuses

Former Member
0 Likes
196

Dear All,

when i am trying to add operation status in IHS work area management, what is the Ops number should give? do i need to configure this number also any where else? When i am trying to add new operation status what ever number i will give it is showing msg as "Choose the key from the allowed namespace ". Kindly help me regard this.

Thanks

Rama Krishna

Accepted Solutions (1)

Accepted Solutions (1)

akash_agrawal5
Explorer
0 Likes

Hi Rama,

The default value of operation status should be 000 in your system. You can add new operation status by entering key as ACT ( for active), DAC, WPL etc, entering such keys should not throw the warning. Moreover, if you have a specific requirement of maintaining only a number in oops key, you can ignore the warning, hit enter and save IMG activity.

Revert if you have any questions.

Regards,

Akash

Former Member
0 Likes

Hi Akash,

thank you for the reply i tried with key, it was working fine and saved the data.even i tried by ignoring msg with specifying number it was working fine.

regards,

rama krishna

Answers (0)