Impacts of Run Down Status on Supply Chain Processes and Maintenance Responsibilities

ga1981
Explorer
0 Kudos
241

Hi Community 🙂 If an SKU is marked as Run Down in SAP ECC/APO at plant level, can existing POs still be received at the destination warehouse with a 101 movement type? What exclusions apply? For example, is production or procurement allowed for this material with RD status? Thank you

View Entire Topic
Prasath
Contributor
0 Kudos

Hello @ga1981 , I understand your question that you want block the future goods receipt for any Opening Purchase order. If this is case, you can please activate plant-specific material status 01 Blocked for procment/whse
which restricts goods receipts from supplier.