on 2023 May 16 9:41 AM
Hi masters,
I'm facing the following situation.
I have this task list with 4 and 8-week tasks.
4 weeks - Check and lubricate
8 weeks - Replace the same component that was checked and lubricated 4 weeks ago.
I wanted to know how I automatically skip the 4 weeks task when the 8-week one is released.
Request clarification before answering.
Hi,
You can use a maintenance strategy for this purpose, you can handle this requirement with the Package Sequence option in maintenance strategy IP11.
Furthermore, refer to this blog
Create Maintenance Strategy in SAP
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks a lot, Raheel.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.