cancel
Showing results for 
Search instead for 
Did you mean: 

How to make Resource field functioning in SAP PPM (Projects)

former_member696173
Discoverer
0 Kudos
369

We have created a Project in SAP Project Management ,Need to add Resources( internal users) to Tasks created in Projects.

For us Resource field is greyed out. To add Resource to Task in Projects should we create Business Partner. How to create Business Partner in S4 Hana SAP projects? What are the prerequisites ?

Thanks inadvace.

Megha.

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

is Checkbox Resource Search activated under Define project Types ?

former_member696173
Discoverer
0 Kudos

Yes did. Issue was fixed.Thanks .

Receiving below error when tried to link existing doc to DMS tab in SAP PPM.Did i missed anything ,what could be issue?

Link Not Possible: No BOM found for this document (Message number 29 731)

Johnny_B_
Active Participant
0 Kudos

Hello,

To my knowledge, in S/4 the business partner is created automatically from the employee master. You definitely need a business partner (role employee) in order to staff it in your PPM project. first create a project role, then staff it with the business partner, and then go to the task do the assignment there.

regards, Johannes

former_member696173
Discoverer
0 Kudos

Thanks for your response Bacher