How to get monthly maintainance schedule on every 30th of month

Former Member
0 Likes
504

Hi Experts

Issue : I want to plan calibration schedule on 30th of each month for scheduling period 12 Months ,On scheduling plan ,its giving me schedules on 30th of months for period before Feb month ,but after Feb  this gives schedule on 28th of each month for months following Feb.

Maintenace Plan set up

Scheduling indicator: Time -Key date

Start of cycle: 10/30/2012

Scheduling period :1 Yrs

On plan schedules are thrown like this

Call    Plan Date    

1      11/30/2012

2      12/30/2012

3       01/30/2013

4       02/28/2013

5       03/28/2013

6       04/28/2013

I want plan dates for month 03 and 04 as 30th not as 28th of month

Thanks in advance

This is urgent ,Pls help ASAP

Thanks

Upinder

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Likes

Hi Upinder,

The cause of the issue is reflected in the fact that once 28th February 2013 is scheduled, the system treats the last day of February, 2013 as an updated value (28). Hence you see the rest of the schedule calls starting from the 28th of each month.

Please note that using Scheduling Based on Key date, it is suggested not to define a key date later than 28 of a month, exactly for this reason.

You can possibly use Adapting a planned date function to maybe fulfill your business needs. The work around could be tedious but a manual adjustment can be performed.

Hope this helps!

Cheers

Upi

Former Member
0 Likes

Hi

Thanks for response

Can you pls explan suggested solution little a bit

You can possibly use Adapting a planned date function to maybe fulfill your business needs. The work around could be tedious but a manual adjustment can be performed.

I am not able to understand.

Thanks once again.

Upinder

Former Member
0 Likes

Good Morning Upinder,

As for the Adapting a planned date function individually (Following info as available in the standard SAP help)

You can use the customer exit IPRM0002 to adapt a planned date calculated by the system individually, and, for example, represent seasonal variations for counter readings.

Features

The following function modules are available:

  • For counter-based maintenance: EXIT_SAPLIPM5_001
  • For time-based maintenance: EXIT_SAPLIPM5_002

You can also you the Call Horizon to check if the scheduling matches your requirement but that would mean that you will have to do a mass update of scheduling horizon for the month of Feb, 2013 and update the call again in March, 2013.

Planned DateCycleCycle Modification FactorChanged CycleCall Horizon planned date (Simulated)
30/10/12 1
30/11/12 1
30/12/12 1
30/1/13300.9929.728/2/13
28/2/13301.0230.630/3/13
30/3/13 1
30/4/13 1
30/5/13 1
30/6/13 1

Try and see if this solution works for your maintenance plan by using IP10 and simulate the dates for one of the plans.

Currently I don't have access to a system to simulate the same but this could be one of the solutions to try.

Hope this helps and let me know in case you need any more info.

Cheers

Upinder