on 2013 Feb 19 5:29 PM
Hi Gurus,
We have a project in SAP PPM 5.0.
We want to assign the resource to this project.
We do not want to let assign the resource.
We want to have a additional approval for assigning the resource.
Is this possible?
Regards
Dieter
Request clarification before answering.
Hello,
Yes it is possible, when you define the role type configure it with staffing process.
Then you need to define organizational structure to the staffing manager approve this assigment.
Let me know if you need furgher information.